Multi-million-pound coal tip safety work begins in Rhondda
Coal tip safety work begins in Rhondda with road closure

Multi-million-pound works to make a coal tip in the Rhondda safe are set to begin, involving a local road closure and diverted bus services.

Work starts July 27 on Graigddu Tip

Rhondda Cynon Taf Council has said work will start from Monday, July 27 and last around 13 months on a major scheme at Graigddu Tip in Dinas, delivering multi-million improvements to stabilise ground conditions at the former coal tip.

The council said significant Welsh Government funding support has previously been received for the work, which will be delivered under a local road closure and using temporary bus arrangements.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Contractor appointed and design details

In February 2026, the council awarded a design and construct contract to Alun Griffiths (Contractors) Ltd, with the council having received a £4.8 million funding commitment from the coal tip safety multi-year grant scheme running up to 2029/30. The contractor has been supported by consultants Stantec to carry out additional investigatory work, prepare the scheme’s design, and gain the required permissions to bring the final scheme forward for delivery.

The council has now appointed Alun Griffiths (Contractors) Ltd as the main project contractor, and work will start on site from Monday, July 27.

Scheme details and road closure

The scheme is designed to provide protection to Graigddu Road and Vicarage Road by installing an anchored piled wall along the toe of the tip. A series of drainage improvements will also be carried out, with localised stabilisation on the tip above.

The work will take approximately 13 months to complete and will require a necessary, local road closure at Graigddu Road and Vicarage Road. There is an alternative route via Vicarage Road and Dinas Road, but access cannot be maintained for emergency services, pedestrians nor premises. A temporary access road will be created by the contractor to maintain access for the residents of the four properties at Graigddu Farm. The road closure is needed due to the presence of large machines such as piling rigs, cranes, excavators and lorries, which need to be operated safely.

Bus diversions and community contact

The 173 Stagecoach and Thomas of Rhondda bus services (Porth-Clydach Vale) will be diverted via B4278 Dinas Road during the works. Contractor Alun Griffiths Ltd has also provided a dedicated liaison officer, Neil Evans, to answer queries from the community. This officer can be contacted via phone (01873 857211) or email (enquiries@alungriffiths.co.uk).