Capability Scotland cannot start its £28 million development of a care home until it secures ownership of the Perth Leisure Pool site it is being built on. Last week, Perth and Kinross Council's Planning and Placemaking Committee approved planning permission - by a single vote - for a 60-bed care home to be built on what is currently the play area and car park at Perth Leisure Pool.
Around 10,000 people signed a petition, both physically and online, calling for the site - gifted for leisure purposes - to continue being used for leisure. On November 11, councillors voted by six votes to five to approve the plans and what was deemed by council planning officers as a "minor" departure from its local development plan. The site formed part of a wider area allocated for "railway station, leisure and hotel" in Perth and Kinross Council's local development plan.
Land Transfer Still Pending
Following the decision, a Capability Scotland spokesperson said: "Capability Scotland will continue working with Perth and Kinross Council to progress the outstanding arrangements for the transfer of the Glover Street site." Perth and Kinross Council confirmed a council committee will be asked to approve the land transfer at a later date.
A PKC spokesperson said: "Decisions on the sale or transfer of the land at Glover Street required for the Capability Scotland development will be considered separately at a future meeting of the relevant council committee." PKC's Property Sub-Committee met to consider a property matter - in private - on Monday, November 16 but PKC confirmed the Capability Scotland development site at Glover Street was not discussed then.
There is a risk to the development if councillors vote to refuse transferring the land ownership to Capability Scotland, which brings into question if voting on the application was putting the cart before the horse. Further to the question mark over the order of the entire process, a Save Perth's Sports and Leisure Centre at Glover Street campaign spokesman said: "The logical way would have been to get planning permission for Thimblerow first."
PH2O Project at Earlier Stage
The council's controversial plan is for the replacement leisure and swimming pool facility, PH2O, to be built on Perth's Thimblerow car park. However it is at a much earlier stage of the planning process with no pre-application report as yet. PKC has confirmed land or property ownership is not required in order for a planning application to be submitted. A council spokesman pointed to a recent example of the Wee Choo Choo restaurant being established in part of a Perth and Kinross Council car park in Pitlochry.
The council spokesman added: "However, if permission is granted and you don’t own or have an agreement to use the land, you can’t do anything." Previously, PKC planned to build PH2O on the Glover Street site. But in September 2024, councillors were told a tandem build with both Dewars Centre and Perth Leisure Pool remaining open to the public would be "extremely challenging".
PH2O project manager John Fyfe told councillors: "It would be extremely challenging. You'd immediately lose most of the car parking and I don't think any contractor would be comfortable with the amount of visitors going across the construction site." At last week's planning meeting, PKC's Major Applications and Enforcement team leader Sean Panton said that was a "significant time ago" and that "things have evolved since then".
Council Defends Site Choice
Things appear to have evolved within less than a year, as in June 2025 councillors were asked to approve the Capability Scotland development on the Glover Street site instead. When this reasoning was challenged at last week's meeting, PKC's Legal manager Geoff Fogg told the Planning and Placemaking Committee the reason was this build did not involve another leisure pool. He said the Capability Scotland development was "quite different from the challenges of building another pool".
But this reason also did not appear to hold water, considering this is exactly what PKC just did at Blairgowrie with the tandem build of its £36 million Blairgowrie Recreation Centre (and its replacement pool), which opened in August 2025. When the Local Democracy Reporting Service questioned PKC on this, a spokesman said: "The Capability Scotland [development] is on a different part of the site than would have been used for PH2O. Blairgowrie Recreation Centre was built on land behind the old Rec Centre (and is a completely different site)."
Capability Scotland's chief executive Brian Logan said the charity was following the "appropriate planning process". Mr Logan said: "The planning application for Our Inclusive Community Project has been considered and approved by Perth and Kinross Council following the appropriate planning process. Our focus remains on delivering a much-needed, purpose-built community that will provide high-quality accommodation and support for adults with complex needs in Perth. We will continue to work closely with the council and other partners as the project progresses."
Following last week's vote, a Save Perth's Sports and Leisure Centre at Glover Street campaign spokesman this week expressed his "extreme disappointment and hopes that some clarity of thought will rear its head". He added: "We're not done. This battle has been lost but the war is not over."