Shotley Bridge Hospital replacement size fears amid Consett growth
Shotley Bridge Hospital size fears amid population growth

Concerns have been raised that a scaled-back replacement for Shotley Bridge Hospital will not be able to cope with a "population explosion" around Consett, as Durham County Council prepares its next development blueprint for the county.

The worries come as proposals for the new hospital are being reduced by approximately 20 per cent, while the existing facility has once again stopped providing overnight urgent care due to staffing pressures.

Councillors question hospital capacity

Cllr Kenny Hope highlighted what he described as a "population explosion" around Consett as he questioned whether local health services would be able to cope with the strain. He noted that the population had grown by thousands in the decade preceding 2021, adding: "I know the explosion has been massive, [with] many, many developments, especially within [Delves Lane]."

Cllr Mark Wilkes then raised doubts over whether the proposed replacement hospital would be sufficiently sized to serve an expanding population.

"We've had that meeting where the NHS has said we're looking at, what, three or four years before we'll end up with the new hospital, which is not as big as what most people in the area wanted," he said.

"But how are we making sure that when you're analysing this and when we're looking at the NHS, they're actually building a hospital that is going to be capable of taking whatever the future number of people who live in that area?"

Council and NHS planning

James Cook, Durham County Council's planning policy manager, said: "When we are looking at Consett in particular, if there are sites which are identified, we would expect the NHS to have that conversation with us." He further stated that the availability of healthcare facilities in an area would be taken into account when evaluating potential development proposals.

The concerns emerge following County Durham and Darlington NHS Foundation Trust's announcement that the new Shotley Bridge Hospital would be roughly 20 per cent smaller than originally intended. The trust has submitted an application to Durham County Council to modify the designs, with departments reduced from 15 to 12 and 35 rooms removed. It maintains that the planned range of services will be preserved.

Meanwhile, the existing hospital's urgent treatment centre will remain closed between midnight and 8am until the end of March 2027 due to ongoing difficulties in safely staffing the night shift. The overnight service had resumed in April following a nine-month closure but was suspended once again in October.

Delays and rising costs

Plans for the replacement hospital have also been dogged by years of delays and escalating costs. Last month, trust chief executive Steve Russell told councillors he could not guarantee it would be completed by 2029. He said: "The timetable is currently 2029, but I can't really guarantee it will be 2029 because there's a set of unknowns."

The discussion arose as the council weighs up around 850 sites put forward for possible development as it draws up its new local plan. Its yearly housing target has risen from 1,308 to 2,036 homes, with the council calculating that land for approximately another 8,000 properties will need to be identified.