Multi-million pound scheme approved to stabilise high-risk Merthyr coal tip
Multi-million pound scheme approved for Merthyr coal tip

A multi-million-pound scheme to stabilise a coal tip in Merthyr Tydfil has been approved as the most practical and sustainable long-term solution for managing it and protecting the nearby community.

The Nant Yr Odyn coal spoil tip, located above Pentrebach in the south of Merthyr Tydfil county borough, is classified as a high-risk category D coal tip and contains approximately one million cubic metres, or 1.85 million tonnes, of colliery spoil.

Why the scheme is needed

Recent extreme weather events, ongoing groundwater drainage issues and flooding incidents have highlighted the need for a long-term management strategy to reduce geotechnical, environmental and community risks, according to a cabinet report.

Extensive ground investigation, monitoring and a feasibility study have been carried out, and six options were assessed against safety, environmental, social and economic criteria.

Members of the council's cabinet on Wednesday, November 25, approved the preferred option of re-profiling and stabilisation of the tip with selective removal of spoil to deliver a robust and sustainable solution by addressing both geotechnical and environmental risks to ensure long-term safety.

Community concerns and historical findings

Councillor Gareth Lewis, who represents the Plymouth ward which includes Pentrebach, said the report was about protecting local residents and providing reassurance to a community that has experienced the consequences of major flooding.

He said for those affected by storms such as Dennis and Bert it brought disruption to family life, the stress and inconvenience of recovering from the flooding, and the constant worry that further heavy rainfall could result in a repeat of their experiences.

Cllr Lewis said he was pleased to see the considerable amount of work that had been carried out to better understand the challenges associated with the tip, adding that the preferred option appears to provide a sensible balance between public safety, environmental considerations, and deliverability.

Following engagement with the Mining Remediation Authority in January 2025, historical evidence was found which shows that the tip was formed over three natural watercourses. Due to extensive mining activity in the area and changing weather patterns with increased rainfall events, this has created complex drainage conditions both within and around the tip.

A decision was then taken to increase the frequency of inspections at Nant Yr Odyn, and the council has been carrying out flood alleviation works in the vicinity of the tip. An advanced monitoring system is also operating 24 hours a day and will alert of any movement within the tip.

Ground investigation and feasibility study

A ground investigation by Earth Science Partnership, which concluded in April 2026, produced a detailed model of the site. The site is also designated as a site of importance for nature conservation (SINC) with habitats to potentially support bats, otters, badgers, reptiles, great crested newts, and other protected species.

Water quality investigations identified elevated metals, hydrocarbons, and polyaromatic hydrocarbons in some samples, needing further assessment. Some spoil material shows combustible characteristics meaning precautions will be needed during any earthworks, but no unacceptable human health contamination was identified.

Coal recovery was assessed as commercially unviable due to low residual coal content, and slope stability monitoring and analysis showed no evidence of significant downhill movement. Recorded movements were generally less than 5mm and are considered likely to reflect instrument settlement rather than slope instability.

The tip is not currently showing evidence of active large-scale movement, but the report said that without remediation, significant increases in groundwater levels could reduce overall stability and increase failure likelihood in the future.

Following the outcome of the ground investigation report, consultants WSP were commissioned to carry out a feasibility study for a proposed remediation strategy, involving drainage improvements, re-profiling and engineered stabilisation. The feasibility study report assessed six reclamation and stabilisation options, from minimal intervention through to complete removal and relocation of the tip.

Preferred option and next steps

The six options were to do nothing, maintain the tip with enhanced drainage and monitoring, install directionally drilled under-drains, re-profile and stabilise the tip with selective removal of spoil, temporary removal and engineered replacement of spoil, and the complete removal and relocation to a receptor site.

The report concluded that the do nothing and limited intervention approaches would not adequately address long-term stability and flood risk. It also concluded that while complete removal would provide the highest level of risk reduction, the significant cost, environmental impact, planning complexity and programme duration make it a less favourable solution under current circumstances.

The preferred option is re-profiling and stabilisation with selective removal of spoil. This would involve removing approximately 100,000 to 140,000 cubic metres of material from critical areas of the tip, focusing on the upper and mid-slope areas contributing most to instability, as well as re-grading slopes to improve stability, upgrading drainage infrastructure to reduce flood risk and undertaking ecological and landscape enhancements.

The estimated construction cost is approximately £4-5m. Removal of approximately 20% of the tip will require spoil material being relocated to a receptor site. Three potential receptor sites have been identified: receptor site one is situated directly above Nant Yr Odyn tip on a plateau of gently sloping ground with capacity for 180,000 cubic metres of material; receptor site two is situated to the south of receptor site one on a plateau of gently sloping ground with capacity for 180,000 cubic metres; and receptor sites 3a and 3b are former quarry areas located to the south of the tip, with site 3a having capacity for 35,000 cubic metres and site 3b having capacity for 20,000 cubic metres of material.

The cabinet report said: "While significant planning, ecological, and regulatory challenges remain, this option provides the most practical and sustainable long-term solution for managing the Nant Yr Odyn Tip and protecting the nearby Pentrebach community."

The report added: "In conclusion, the implementation of a carefully designed re-profiling and stabilisation scheme represents the most appropriate course of action for Nant yr Odyn Tip. It provides a robust, achievable and cost-effective solution that addresses the principal geotechnical, drainage and flood risk concerns while supporting environmental enhancement and safeguarding the local community for the long term future."

It also stated: "Welsh Government remains fully informed of the current situation at Nant yr Odyn and continues to receive updates on progress. A three-year funding programme has been secured to facilitate the progression of the preferred re-profiling and stabilisation option. This funding will support the continued development of the scheme, including ongoing engineering, geotechnical, environmental and design work by WSP, together with the delivery of the associated construction and stabilisation works required to improve the long-term safety and resilience of the tip."