Wirral councillors have approved a £36.5m contract to start enabling works on the Borough Yard development in Birkenhead, a major regeneration project set to deliver up to 1,600 new homes close to the town centre.

The scheme will transform the former gasworks site between Birkenhead Central and Green Lane Merseyrail stations into a new urban community. The council's policy and resource committee met on Wednesday, November 18, to discuss the next stage of the project.

Contract approvals and next phase

The committee approved the appointment of John Sisk & Son Ltd to carry out enabling works with a contract worth £36.5m. Councillors also approved a £2.86m agreement with Ion Property Developments Ltd for the management and implementation of those works.

The next phase includes further site remediation and engineering works, the installation of a United Utilities attenuation tank and the relocation of Cadent gas infrastructure.

Political support and concerns

Green Party Cllr Gail Jenkinson said: "We absolutely have to protect our brownfield developments and so this is such a major project going forward. By protecting the brownfield we also protect the green belt. It's a huge relief to see it come forward."

Labour's Cllr Mark Skillicorn highlighted the income and life expectancy inequality between the eastern and western sides of Wirral and said the regeneration of Birkenhead is a significant part of trying to combat that. He warned councillors that not progressing the Borough Yard scheme "could prove devastating for thousands of lives". He added: "I'm not even exaggerating with that."

Funding and wider regeneration

The cost of the project has increased since funding was approved in 2024, when £57.2m was set aside for the scheme. This funding was set to largely come from Homes England and the Liverpool City Region Combined Authority (LCRCA), with a contribution also coming from Wirral Council.

A further £8.9m is now required, which will come from the combined authority. The LCRCA approved a re-allocation of funding to meet this need at a meeting earlier this month.

Outline planning permission for the scheme, which includes the demolition of two flyover roads near Birkenhead Central, was granted in early 2025. The project is set to tie into other regeneration projects in the town including the new Birkenhead Market, which is set to open in February. The project will also link up with the proposed linear park that is set to connect Birkenhead's docks to Green Lane station. Inspired by The High Line in Manhattan, the park will follow the route of a disused railway line.