A resident with respiratory issues at a 19-storey tower block in south London says he feels like a “prisoner in [his] own building” because a lift has not worked since early 2025.
Tariq Naquy, who lives on the 19th floor of Amesbury Tower on Wandsworth Road, Lambeth, struggles to use the stairs and has to take a break every few flights to catch his breath.
Only one lift serving even floors
The lift serving the odd-numbered floors reportedly broke down in February 2025, leaving residents reliant on the building’s only other working lift, which serves the even floors. Residents are worried this remaining lift is also reaching the end of its life because it is prone to frequently breaking down.
Many residents, including elderly people, those with health conditions, and young families, have to climb the stairs and hold on to the railings. They describe it as a “nightmare” when returning with bags of shopping.
Residents' fears and council response
Tariq told the Local Democracy Reporting Service (LDRS): “When there were two [lifts], you’re all right because if one has conked out, you’ve got the other one as backup. But when one has been out for [nearly two years] and you’re watching this other one conking out and showing the same symptoms as the other one; if they can’t repair that and that goes out and they can’t repair the other one either, then what happens to us at the top?”
He added: “When you see women with their children and you’re trying to jump in and help them out, you can see how vulnerable this situation is – you just feel like a prisoner or slave in your own building.”
Lambeth Council applied for permission to replace the lift in February 2026, but the Building Safety Regulator (BSR) reportedly extended the deadline to approve it three times, adding 26 weeks in total. The BSR oversees and approves building work for ‘higher-risk buildings’, which are seven storeys or more, at least 18 metres high, and contain at least two residential units or are a hospital or care home.
The council reportedly asked the BSR to fast-track the application as a matter of urgency, but the request was declined because the regulator did not consider the work to meet its criteria for an emergency.
Residents' struggles and political support
Ann Shew, who lives on the 15th floor and has osteoarthritis and spinal stenosis, said: “I’ve had three knee operations, so it’s a bit of a chore. Every time you use the stairs, it’s impacting. I had a knee replacement two years ago in 2024, and for the last few days it’s really been hurting because I’m constantly using the stairs.”
She added: “Every time there’s a lift breakdown, we have no one to contact, no one to fall back on. You’ve got to carry your shopping up the stairs, you’ve got disabled people who can’t get in or out, elderly people can’t leave their flats.”
Neil Salt of the Lambeth Conservatives has been supporting residents by demanding the BSR treat the lift works as an emergency matter. He said: “This is a 60-year-old building. Inevitably, the lifts are going to go out of order. The one that’s working is getting double the amount of usage clearly because the other one is out of operation – so that’s another danger point. If anybody tries to hold the lift door open, that creates problems as well. And who’s not going to try and keep the lift door open if they’ve got lots of family members or are waiting for other people to come into the lift? So it’s a real struggle.”
A BSR spokesperson said further information as part of its assessment process was provided on October 30, and is being reviewed by a specialist registered inspector. Additionally, further specialist engineering support was commissioned on October 30 to help progress the application. The BSR spokesperson said: “We are working to progress the application as quickly as possible while ensuring that all necessary building safety requirements are properly considered and that any proposed works meet the required standards.”
A Lambeth Council spokesperson told the LDRS they hope to start the works early in the New Year once approval has been received from the BSR. They said the council is working closely with contractors to ensure that the second operational lift remains in service and available to residents, and have enlisted the help of their guardian service, who are based on the estate, to support any vulnerable residents.
The council spokesperson said: “The council is committed to replacing this lift, which is at the end of its life, and we are doing everything we can to complete the work required. We are aware of the difficulties caused by only having one working lift in this block, and we have apologised to residents for the inconvenience they have experienced as a result.”